Straight answers on cost, permits, size, timing and Hartwell’s low water. Ask us anything that isn’t here.

Lake Keowee from Keowee-Toxaway State Park

The usual questions

CostHow much does a new dock cost on Keowee or Hartwell?

Most new docks here run about $40–⁠$60 a square foot of deck, plus $28–⁠$48 a square foot if it has a roof, $8,000–⁠$15,000 for each boat lift and the walkway. Lake permit fees are on top: about $1,000 on Keowee and $835 on Hartwell.

PermitsDo I need a permit to build or fix a dock?

Yes for a new dock on either lake. On Keowee, Duke Energy says a permit is most likely needed to build, maintain or change a dock too. On Hartwell, the Corps permits the dock and the permit has to be renewed every five years and when the house is sold.

TimingHow long does a new dock take?

Plan on three to four months from the first call: about a month for the permit and two to three months to build. Repairs are often done in a visit or two once any permit is in hand.

Low waterMy Hartwell dock is sitting on the bottom. What can I do?

Get the weight off the floats, then move the dock out to deeper water and lengthen the walkway to reach it. Since August 26, 2026 the Corps holds Hartwell at 656 ft all year, so a dock set for the old summer level may stay short of water. A move runs about $2,000–⁠$6,000 plus $100–⁠$250 for each extra foot of walkway.

SizeHow big can my dock be?

Up to 1,000 sq ft on Keowee, counting the walkway and roof, and up to 1,120 sq ft on Hartwell, not counting the gangwalk, with no side longer than 40 ft. Cove width, neighbors and water depth can make the real limit smaller.

RepairsIs there a minimum charge for repairs?

Yes, a repair visit starts at $350, because every job means getting the work boat and crew to your dock. Several small repairs on the same visit share that cost.

Lake Hartwell

BuyingWhat happens to a Hartwell dock permit when the house sells?

It is void at sale. The new owner has 14 days to contact the Corps' Hartwell office for a new five-year permit, and some grandfathered docks from before 1973 must be removed at sale.

PowerDo I need a licensed electrician for a Hartwell dock?

Yes. The Corps wants dock wiring to meet NEC Article 555 and be certified by a licensed electrician, then re-inspected every five years before renewal. We bring in a licensed electrician for that work.

RoofsCan I put a roof on a Hartwell dock?

Yes, within the Corps' rules: a roof overhang of up to 24 in, no new enclosed structures, and on a two-level slip dock the upper level stays unroofed. As a ballpark, a roof runs $28–⁠$48 per square foot.

Low waterHow low has Lake Hartwell been before?

The record low is 637.5 ft, set in December 2008. In mid-October 2026 the lake read about 649 ft, against a guide curve of 656 ft.

Lake Keowee

RepairsDo I need Duke's permission just to repair my Keowee dock?

Probably. Duke's own FAQ says written authorization is most likely needed for new docks, modifications and maintenance, so check with Duke Energy Lake Services at 800-443-5193 before work starts.

SizeHow long does Duke take to approve a Keowee dock permit?

Local builders report about 20 to 30 days, but Duke publishes no target, so ask Lake Services for the current wait. Once issued, the permit is valid for one year.

FloatsCan I keep the old white foam floats on my Keowee dock?

No. Duke required unencapsulated foam to be removed by September 1, 2018. We use encapsulated flotation, where the foam is sealed inside a plastic shell.

Your lotHow much shoreline does a lot need for a dock on Keowee?

Local builders read Duke's 2014 guidelines as saying lots deeded after September 1, 2006 need at least 100 ft of shoreline. Treat that as a guide and confirm your lot with Duke Energy Lake Services.

Low waterDoes Lake Keowee's level drop in winter?

Not by much. Duke usually holds Keowee within a few feet of full pond at 800 ft, so a floating dock and its gangway see little seasonal change.

New docks

SizeHow long does a new dock take from first call to finished?

One local builder's published estimate is about a month for permits and two to three months to build, so three to four months in all. If you want the dock by summer, start in winter.

WalkwayDoes the walkway count toward the size limit?

On Hartwell it does not: the 1,120 sq ft limit leaves out the gangwalk. On Keowee, local builders read Duke's 2014 guidelines as counting the dock, walkway and roof together toward 1,000 sq ft, so confirm that with Duke Energy Lake Services before you settle on a size.

LiftsCan I add a boat lift later?

Yes, a lift can go on an existing dock, but it is simpler to plan for one from the start so the slip is the right size. A lift installed with a new dock runs about $8,000–⁠$15,000 as a ballpark.

GeorgiaDo you build docks on the Georgia side of Lake Hartwell?

No. We work on Lake Keowee and the South Carolina shore of Lake Hartwell only.

Dock repair

FloatsHow much does it cost to replace dock floats?

About $150–⁠$400 a float as a ballpark, within the $350 minimum visit. The number of floats and how hard they are to reach set the total.

StormsCan you fix a dock that broke loose in a storm?

Often, yes: new anchors and cables, then repairs to whatever was damaged, as long as the frame is sound. If the frame is bent or rusted through, compare the repair against a new dock first.

RepairsShould I replace old foam floats that aren't encapsulated?

Yes. Bare foam breaks up and sheds into the lake, and a Duke release says unencapsulated foam had to be off Keowee by September 1, 2018.

GeorgiaDo you repair docks on the Georgia side of Lake Hartwell?

No. We work on Lake Keowee and the South Carolina shore of Lake Hartwell only.

Boat lifts

Older docksCan I put a lift on an older floating dock?

Usually, if the dock's frame and flotation can carry the extra weight. We look the dock over and measure the water depth before suggesting one.

Jet skisHow much does a jet ski lift cost?

A PWC port runs about $3,000–⁠$5,000 installed, as a ballpark. On Keowee, local builders read Duke's guidelines as allowing up to two PWC lifts per dock, so confirm with Duke Energy Lake Services before adding one.

Low waterWhy won't my lift lower the boat all the way?

On Hartwell this fall, the likely cause is low water: there isn't enough depth under the lift to float the boat off. A sticking valve or a worn cable can do it too, so a service visit is worth it before you move anything.

PowerDo electric lifts need special wiring?

They need power at the dock, and dock wiring should be done by a licensed electrician; we bring one in. On Hartwell, the Corps requires wiring to NEC Article 555, certified by a licensed electrician.

Dock relocation

Low waterWill Lake Hartwell come back up to 660 ft soon?

Not soon. The Corps expects the saddle dike repair to take five to ten years or more, and until then the guide curve stays at 656 ft with a 662 ft cap.

DistanceHow far out will my dock need to go?

That depends on how fast your lake bed drops away, which is why we measure the depth along your shore before pricing a move. On a gentle slope it can be a long way; on a steep bank, only a few feet.

PermitsDoes moving my dock change my Shoreline Use Permit?

The dock has to stay within your permit, so call the Hartwell lake office at 706-856-0300 before anything moves. Ask whether the new position needs their approval.

DamageCan a dock sitting on the bottom be damaged?

Yes. When floats rest on mud or rock the frame takes loads it wasn't built for and can twist, and the walkway hinge takes extra strain.

Riprap and shoreline

The bankCan I build a seawall on Lake Keowee?

Not on banks 2 ft high or less, as local builders read Duke's guidelines, which allow only enhanced riprap or bioengineering there. Confirm what your lot allows with Duke Energy Lake Services at 800-443-5193.

TimingWhen is the best time of year to place riprap?

On Keowee, Duke's guidelines, as local builders read them, rule out stabilization from March through June in Impact Minimization Zones, so plan around that window and confirm it with Duke. On Hartwell, low water leaves more of the bank exposed to work on.

PermitsDoes riprap need a permit?

Yes: Duke's written authorization on Keowee, plus a state stabilization permit where one applies, and the Corps' approval on Hartwell. We draw the plan and profile and file the application for you.

GeorgiaDo you do shoreline work on the Georgia side of Lake Hartwell?

No. We work on Lake Keowee and the South Carolina shore of Lake Hartwell only.