New docks run about $40–⁠$60 a square foot of deck, with a roof adding $28–⁠$48 a square foot. Both are ballpark ranges, not quotes.

Lake Keowee in autumn, with a covered dock at the water's edge below a lawn

We build floating boat docks on Lake Keowee and the South Carolina shore of Lake Hartwell: open docks, covered slip docks and two-level docks. Duke Energy and the Army Corps of Engineers set different limits, so we size every dock to its lake’s rules before we draw it.

How much does a new dock cost?

Our ballpark is $40–⁠$60 a square foot of deck, plus $28–⁠$48 a square foot for a roof. The walkway and any lift are priced on top.

ItemBallpark
Dock, per sq ft of deck$40–⁠$60
Roof, per sq ft$28–⁠$48
Walkway under 20 ft$2,500–⁠$5,000
Walkway over 40 ft$9,000–⁠$15,000
One lift, installed with the dock$8,000–⁠$15,000

The water inside a slip is not deck, so you don’t pay deck rates for it. For comparison, HomeGuide puts floating docks at $15–35 a square foot nationally, before roofs and lifts. Ours are ranges, not quotes: the framing, the decking and the length of walkway your bank needs set the real number. The Keowee and Hartwell dock cost guide goes line by line.

Should the frame be steel, aluminum or wood?

For most docks here, galvanized steel or aluminum. Builder comparisons usually sum them up like this:

FrameThe usual take
Galvanized steelLower cost, heavier, steadier in wake
AluminumCosts more, lighter, little upkeep
WoodBest kept to small platforms

The same comparisons note that roofed docks are usually steel or aluminum.

Pressure-treated pine or composite decking?

Pine costs less up front. Composite costs more and needs less care. ShoreProtect’s figures for an installed dock run $40–75 a square foot all-in with pressure-treated pine and $60–95 with composite. Pine needs sealing, and the odd board replaced as it ages. Composite won’t rot, but it gets hot in July sun, so lighter colors are kinder to bare feet.

What keeps the dock afloat?

Encapsulated flotation: foam sealed inside a hard plastic shell, so it doesn’t crumble into the lake or soak up water. We use encapsulated flotation. A Duke release says unencapsulated foam had to come out of Keowee by September 1, 2018, and Hartwell’s 2020 Shoreline Management Plan requires marine-grade flotation warranted for at least eight years.

How big can a dock be on each lake?

On Keowee, builders put it at 1,000 sq ft with the dock, walkway and roof counted together. On Hartwell, the Corps allows 1,120 sq ft, not counting the gangwalk.

RuleLake KeoweeLake Hartwell
Size1,000 sq ft including walkway and roof1,120 sq ft, gangwalk not counted
ShapeUp to 120 ft long, no more than a third of the way across the coveNo side over 40 ft, at least 10 by 20 ft
LevelsOne story, with an unroofed sundeckSlip docks may have two levels, the upper one unroofed

The Keowee column is how local builders and realtors read Duke’s 2014 shoreline guidelines, not Duke’s own wording, so confirm it with Duke Energy Lake Services (800-443-5193) before you plan around it. The Hartwell column is from the Corps’ 2020 Shoreline Management Plan, which also asks for docks perpendicular to the shore, at least 50 ft from other facilities, with roof overhangs of 24 in or less.

What does the permit take?

We visit the site and measure water depth, draw the plan and profile, and file the application with Duke Energy or the Corps for you.

On Keowee, Duke’s written authorization comes through its online LAPS system, with a registered survey, the drawing and county building permits. Duke’s January 2025 fee schedule and builders’ reports put new-dock fees at $1,000, Duke’s fee plus a habitat fee, with approval in about 20 to 30 days. Confirm both with Lake Services. The permit is valid for one year.

On Hartwell, you need a five-year Shoreline Use Permit. You meet the ranger with the deed, plat, plans and fee, reported as $835; confirm it with the lake office at 706-856-0300. The plans need a state-licensed structural engineer’s approval, and the lot must share at least 75 ft of boundary with green Limited Development land.

More in Lake Keowee dock permits and Lake Hartwell dock permits.

What connects the dock to the bank?

A walkway or hinged gangway, plus cables and anchors that let the dock ride up and down with the lake. On Hartwell, low water can mean a longer walkway; see moving a dock to deeper water. For lifts, see boat lifts. For power, we bring in a licensed electrician; Hartwell requires wiring to NEC Article 555, certified by one.

For a ballpark on your lot, try the dock estimator or call (424) 423‑9302. We’ll come out, measure the water and draw it up.

Quick answers

SizeHow long does a new dock take from first call to finished?

One local builder's published estimate is about a month for permits and two to three months to build, so three to four months in all. If you want the dock by summer, start in winter.

WalkwayDoes the walkway count toward the size limit?

On Hartwell it does not: the 1,120 sq ft limit leaves out the gangwalk. On Keowee, local builders read Duke's 2014 guidelines as counting the dock, walkway and roof together toward 1,000 sq ft, so confirm that with Duke Energy Lake Services before you settle on a size.

LiftsCan I add a boat lift later?

Yes, a lift can go on an existing dock, but it is simpler to plan for one from the start so the slip is the right size. A lift installed with a new dock runs about $8,000–⁠$15,000 as a ballpark.

GeorgiaDo you build docks on the Georgia side of Lake Hartwell?

No. We work on Lake Keowee and the South Carolina shore of Lake Hartwell only.