The shoreline around Lake Hartwell is managed by the US Army Corps of Engineers, Savannah District, and a private dock needs the Corps’ Shoreline Use Permit. The rules come from the 2020 Shoreline Management Plan, in effect since November 15, 2020. We build on the South Carolina shore only, in Anderson, Oconee and Pickens counties, so this guide is written for SC lots.
Can I put a dock on my Lake Hartwell lot?
Only if the lot shares at least 75 ft of boundary with shoreline the Corps has allocated as Limited Development, shown green on its maps. The Corps allows one dock per deeded lot.
| Map color | Allocation | New private dock? |
|---|---|---|
| Green | Limited Development | Yes, with 75 ft of shared boundary |
| Yellow | Protected | No |
| Red | Public Recreation | No |
| Orange | Prohibited Access | No |
How do I check my lot’s allocation?
Look the lot up on the Corps’ Hartwell allocation maps or call 888-893-0678. The Hartwell lake office is at 5625 Anderson Hwy, Hartwell GA, phone 706-856-0300.
Do this before you buy a lake lot, not after. A lot without green frontage cannot get a new dock, however close it sits to the water. Our guide to buying a lake house with a dock covers what else to check.
How does the Hartwell permit process work?
You meet the Corps ranger with your deed, plat, plans and fee. The plans need approval from a state-licensed structural engineer first.
- Confirm the lot is green, with at least 75 ft of shared boundary.
- Measure the water. Local builders cite a minimum of 4 ft of water at the gangwalk connection; confirm it with the lake office.
- Draw the plan and profile, and have a state-licensed structural engineer approve them.
- Meet the ranger with the deed, plat, approved plans and fee.
- Have a licensed electrician certify any wiring (see below).
We visit the site and measure water depth, draw the plan and profile, and file the permit application with the Corps for you. With the lake running low, depth needs care; see what low water means for Hartwell docks.
What does a Lake Hartwell dock permit cost?
$835 for a new or reissued Shoreline Use Permit, the latest fee the Corps has published. Confirm it with the lake office before you budget.
The older fees were $400 for a new permit and $175 for a renewal. A 2019 postponement of the increase was reported, and what happened after is unclear, so ask the lake office (706-856-0300) for the current fee before you budget. The Corps’ shoreline management page has the background. For the dock itself, see dock costs on Keowee and Hartwell.
How long does a Hartwell dock permit last?
Five years. It does not pass with the house: the permit is void at sale, and the new owner must contact the lake office within 14 days to get a new five-year permit.
Some docks grandfathered from before 1973 must be removed when the house sells, and the owner then has six months to install a replacement.
What are the Hartwell dock design rules?
The 2020 plan caps a private dock at 1,120 sq ft, not counting the gangwalk, with no side longer than 40 ft and nothing smaller than 10 × 20 ft. The full rules are in the 2020 Shoreline Management Plan.
| Rule | Limit |
|---|---|
| Size | 1,120 sq ft, gangwalk not counted |
| Longest side | 40 ft |
| Smallest dock | 10 × 20 ft |
| Layout | Perpendicular to the shore |
| Spacing | At least 50 ft from other facilities |
| Enclosures | No new enclosed structures |
| Roof overhang | Up to 24 in |
| Levels | Slip docks may have 2, upper level unroofed |
| Flotation | Marine-grade, warranted at least 8 years (condition 14) |
| Anchoring | To the shore, with a gangwalk and cables |
| Roof colors | Dark green, black, brown or gray (confirm) |
We use encapsulated flotation. The roof color list is how local builders read the plan, so confirm it with the lake office before you choose roofing. The 40 ft side limit matters for long, narrow docks: they can hit it well before the size cap.
What are the electrical rules for a Hartwell dock?
Dock wiring must meet NEC Article 555 and be certified by a licensed electrician. On public land it needs GFCI protection.
Wiring is re-inspected every five years before the permit is renewed, for permits expiring on or after February 1, 2021. Solar DC systems are exempt. We bring in a licensed electrician for dock wiring.
How is Hartwell different from Keowee?
Hartwell’s rules come from the Army Corps. Keowee’s come from Duke Energy, with a one-year permit and, as local builders read Duke’s guidelines, a smaller size cap.
| Rule | Lake Hartwell | Lake Keowee |
|---|---|---|
| Who permits | Army Corps of Engineers | Duke Energy |
| Size cap | 1,120 sq ft, gangwalk excluded | 1,000 sq ft, walkway and roof included (Duke 2014 guidelines, as builders read them) |
| Permit term | 5 years | 1 year |
| Fee, new dock | $835 (confirm) | $1,000 (confirm) |
The full Keowee rules are in our guide to Lake Keowee dock permits, and our Lake Hartwell page has more on this lake.
We work on the SC shore, from Clemson and Anderson to Fair Play. For a ballpark on a Hartwell dock, use the dock estimator or call (424) 423‑9302 to arrange a site visit.